Critical Path Schedule

What is a Critical Path Schedule in CPM
A Critical Path Schedule is a key component of the Critical Path Method (CPM), a project management technique used to plan and manage complex projects.
The Critical Path Schedule identifies the sequence of activities and tasks in a project that must be completed on time in order to ensure that the project is completed within its specified timeframe.
These tasks are considered critical because any delay in their completion would directly impact the project’s overall schedule.
Key Elements of a Critical Path Schedule
1. Activity List
This is a comprehensive list of all the tasks and activities required to complete the project. Each activity is typically defined by a description, a duration, and any dependencies on other activities.
2. Network Diagram
A network diagram is used to visually represent the project’s activities and their dependencies. It typically consists of nodes (representing activities) and arrows (representing the sequence and dependencies between activities).
3. Duration Estimates
Each activity on the Critical Path Schedule should have a duration estimate, which is the amount of time it is expected to take to complete the activity.
4. Dependency Relationships
Activities are linked by dependencies, which define the order in which they must be completed. These dependencies can be of two types:
- Finish-to-Start (FS): The dependent activity can only start once the preceding activity has finished.
- Start-to-Start (SS): The dependent activity can start as soon as the preceding activity has started.
- Finish-to-Finish (FF): The dependent activity can only finish when the preceding activity has finished.
- Start-to-Finish (SF): The dependent activity can only finish when the preceding activity has started.
5. Critical Path
The critical path is the longest sequence of dependent activities that determines the shortest time in which the project can be completed. Activities on the critical path have zero slack or float, meaning any delay in these activities will result in a delay in the overall project.
6. Slack or Float
Activities not on the critical path may have some slack or float, which is the amount of time they can be delayed without affecting the project’s completion date. Activities on the critical path have zero slack.
7. Project Duration
The Critical Path Schedule will indicate the total duration required to complete the project, based on the activities and their dependencies. This is typically the duration of the activities on the critical path.
Critical Path Schedule
By creating and maintaining a Critical Path Schedule, project managers can effectively plan, monitor, and control project timelines. It helps in identifying potential delays and allows for better allocation of resources to ensure that critical activities are completed on time, thus ensuring the successful and timely completion of the project.
Here are some Critical Path Schedule Advantages.
Here are some Critical Path Schedule Disadvantages.